Hi
I am in trouble about Optimizer and Order Date.(Avail/Req Date)
[What I want to do]
After executing Optimizer, Order date for in house should be middle of the Month.
# Time Bucket is Month
[Current situation and Configuration]
Currently the order date is always middle of the month. (eg. 15th June 2013)
Configuration
1.SNP Optimization Profile
Bucket Offset During Production: 0.5
Bucket Offset During Shipment: 0.5
2.Product master/ Lot Size Tab
Period Factor:0.5
#It seems this value is nothing to do with Optimizer
This is only for Heuristic.
Someone, please advice me if you know other neccesarry configuration.
Regards