Creation of SNP PDS using planned delivery time

$
0
0

Dear Experts,

 

How do i control creation of PDS because of operaion generated from planned delivery time,although planed delivery ime is zero.

the scenario is as follows:

 

Material :XXXXX

Planned Delivery time

Procurement Type:E

Plant:XXXX

in transaction /sapapo/curto_simu: there are two PDS displayed with PDS usage as PDS for Supply Network Planning(SNP)

the first one is because of operation generated fromm planned delivery time,output qty is the same a s that maintained as base qty in BOM and mode is blank,activity field is even blank.

the other PDS is created because of the valid production version in R/3.

 

Thanks in advance

 

Amrish