Quantcast
Channel: SCN : Discussion List - SAP Advanced Planning & Optimization (SAP APO)
Viewing all 2068 articles
Browse latest View live

Gaps Between Orders while Rescheduling in DS Board

$
0
0


Hi All,

 

After rescheduling is carried out on DS board , I observe that there are gaps between orders on the resource and the sequence of orders have been changed.I am planning in forward direction and the scheduling mode used is insert operation.

 

I need help in understanding the presence of gaps and why does rescheduling change sequence of orders.

 

 

Thanks,

Shweta


Error in Alerts in DS Board

$
0
0


Hi All,

 

We observe that DS Alerts run from DS board are picking up resource alerts from plants that are not included within work area.

For example my work areas has plant A, in DS alert monitor under resource view I see alerts are being displayed for plants B, C, D etc as well.

 

Has anyone come across a similar issue ?

 

Appreciate your help.

 

 

Thanks in advance

Shweta

Fiscal year to normal calender days

$
0
0

Hi All,

 

Here is the requirement from the client that, to change the calender from existing fiscal year to normal calender days. So please suggest me what will be the effects of changed it in SAP APO DP.

 

Thanking in advance.

/SAPAPO/SDRQCR21 program is not working correctly if we run the program for range of material and plant wise

$
0
0

Hi APO Experts,

In our project, we have received more sales order inconsistencies which is not clearing by CCR program and it is clearing by  program /SAPAPO/SDRQCR21 with option as Build Reqmts from Doc. Flow, So We have decided to schedule the background job on daily basis for program /SAPAPO/SDRQCR21 with option as Build Reqmts from Doc. Flow, performing the testing in our quality system and observed the below strange behavior. 

When I am running the program /SAPAPO/SDRQCR21 with Range of products and some location range with option as Build Reqmts from Doc. Flow, in Background job. In output it is suggesting to delete one sales order. If I checked that Sales order in ECC, it is for an different location, that is not part of my selection and the order is open. In MD04 the Qty is showing 1 ( as per sales order) but in APO RRP3 view the order qty is showing Zero. I have run the CCR, it is coming in different in content and if I push, the different is not going to APO.

I have tried running the program /SAPAPO/SDRQCR21 with plant which is mentioned in that sales order with option as Build Reqmts from Doc. Flow, in Background job , it is suggesting this sales order under update option correctly.   

Can you please help me understand why it is behaving differently like the location is not part of my selection and why it is suggesting the wrong action. And also whether is it advisable to run the /SAPAPO/SDRQCR21 with option as Build Reqmts from Doc. Flow at plant range and material range in background job.

 

Thanks & Regards,

Sundaram Radhakrishnan

product treatment

$
0
0

Hi

 

heuristics is infinite planning and optimizer factors in resources and does finite planning ,it is a known fact,but my client asked me under what circumstances does a product is subject to heuristics and under what circumstances (business situation ) should we opt for optimizer,i coundt come up with an answer,experts what could be the reason ,my common sense said in optimizer we can get multiple results by modifying config. settings and we can choose the best result but heuristics is rule based gives an answer either as black or white it doesn't offer grey  results ,i know even this is not the exact answer ,could you think of anything other than these two

 

thanks

STO date is not respected

$
0
0

Hi All,

 

We are running MRP heuristic but standard heuristic is not working for us.

 

Example:

 

Happening:

 

Days                          D1     D2    D3    D4

 

Demand                       4      5       7      8

 

Fixed STO                                   18

 

Result after PP run       -       -         -     6

 

 

So STO is getting consider from Ist day it self whereas our requirement is that it should respect the date of STO .

 

Required:

 

Days                          D1     D2    D3    D4

 

Demand                       4      5       7      8

 

Fixed STO                                   18

 

Result after PP run       4       5        -     -

 

 

Please let me know to achive this.

 

 

Thanks,

Krishna

PReqs Created in APO RRP3 not reflected in ECC

$
0
0

Hi experts,

 

We have created purchase requisition in APO RRP3 PP/DS but they are not reflected in ECC.

 

There is already an active IM for the plant-material combination for transactional POs/PReqs

and master data for that. Publishing config for external procurement for the plant is

created. In the IMG for Global parameters and defaults, the "transfer to r/3 ext.

procurement" is already "always create transfer events".

 

Detailed scenario is, we create purchase req in RRP3, activate debug using /h and then click save. Sap Standard calls the FM CALL FUNCTION 'CIF_PO_INBOUND_30A' IN background task destination ECC. This is what creates the queue in ECC.

 

Debugging that created queue, it creates a document number based on the number range for PReqs. [In ECC FM CIF_PO_INBOUND_30A > calls FM CIF_PO_INBOUND > calls FM ME_APO_GENERATE_REQ_PO > calls form requisition_create]

 

Why is this not created in ECC table EBAN and not reflected in MD04?


Why is this order number not reflected back to APO (RRP3) even after calling FM CIF_ORD_KEY_OUTBOUND in the ladder of FMs stated above?

One issue regarding update open Qty. of PO in PP/DS after goods receipt through interface.

$
0
0

Dear experts:

 

We are implementing APO-PP/DS integrated with Non-SAP ERP system, as the standard CIF can’t be used between ERP and APO, we have to use BAPI to transfer data.

 

Now we are facing a problem, after final confirmation & goods receipt of production order in ERP, the open quantity of production order should be updated in PP/DS, but we can’t find any BAPI can help on this.

 

We’ve tried BAPI_MOSRVAPS_CONFHEADMULTI and BAPI_MOSRVAPS_CONFOPRMULTI for production order confirmation, but failed, as SAP said, confirmation without goods receipt will not update the order open quantity. We also tried BAPI_MOSRVAPS_SAVEMULTI3 to change the receipt quantity, but failed, as after partial confirmation, the quantity of production order can’t be changed, but we can’t find a field of “open quantity” (open quantity = total quantity – delivery quantity) in the BAPI. So how can we update the open quantity of production order in PP/DS after goods receipt from ERP?

 

Appreciate for your input, thanks.

 

Regards

Kevin


Copy Key figure data between two planning area with different storage bucket profile

$
0
0

Hi,

I have a DP planning area ' PA1' with monthly storage bucket profile data view 'PA1M' ( monthly TBF) and I want to copy the data to another planning area 'PA2' whose storage bucket is weekly. This would need me to write a custom program which will split monthly to weekly and then populate 'PA2'.

However, In 'PA2', I created two data views 'PA2W' (with weekly time bucket profile) and 'PA2M' (with Monthly Time bucket profile). If I am able to copy the data from PA1 (PA1M) to PA2(PA2M), it will automatically splits monthly to weekly in PA2W.

 

So my question is if there exists a way I can copy key figure data from PA1M to PA2M? Any BAPI?

Incorrect material availability date determination

$
0
0

Hello Friends ,

 

We have one issue with Material availability date . In our system, R/3 fetches the material availability data from APO. We have two materials A & B and for them have enough stock in the plant. We have one FM which determines the material availability date by fetching data from APO . This FM is similar to sales order simulation in VA01 .There are two scenarios here as mentioned below :

 

1) When i run the FM in the morning to check the material availability date for these two materials then it shows today's date for both the materials.

In Debug mode, committed quantity for both materials is greater than zero .

2) When i run the FM in the evening , output shows today's date as material availability date for material-A while it shows tomorrow's date for material-B.

In Debug mode, committed quantity for material A for today is greater than zero while for B, its equal to zero . Hence FM selects next date as material availability date for B . 

There is something related to item level as i have run the FM for both the materials with same customer and plant . In R/3 material master data (MM03) is same for both the materials. Please help me to find out why FM is behaving differently in the evening for the material B.

 

 

 

Regards,

 

Sandeep

Issue with the flow of orders from APO to ECC

$
0
0

Hi Experts!!

 

We are creating planned orders in a Z program through FM /SAPAPO/RRP_ORDER_CREATE_FINDS, which internally uses /SAPAPO/RRP_ORDER_CREATE. However, these orders are being created only in APO and are not flowing to ECC. Presently, we are doing it manually thorough /SAPAPO/CCR. Can anybody please tell me how we can achieve this through FM itself? I have tried exporting IV_APPLICATION as I and E, but that didn't click.

 

Thanks in advance. Your help is highly appreciated.

Macro Help

$
0
0

Hello ALL,

 

I need help on writing a macro for having shipment history but no forecast

 

so for example i need to wirte a macro saying the there should be an alert if there is no forecast but history is there

Table /sapapo/posmapn

$
0
0

Hi Everybody,

I am seeing 48,000,000 entries in this table. Can somebody tell me what is the impact of this on the system performance? Also what is the number of entries that you guys see, if possible?

Thanks,

Subash Nanjangud

CIF activate with out transferring

$
0
0

Hi ,

We have 50000 materials CIF ed successfully in one integration model.But accidentally we deactivated that version to inactive . Because of that we are unable to use change pointers to those 50000 Materials. 


Now how do i activate that version to active with out having to re transfer all the materials again.

 

Thanks,
Srini

SNP Heuristic Capacity leveling is not leveling the capacity with ES category

$
0
0

We are on SCM 7.02 with EHP2.

 

We are using standard SAP SNP subcontracting functionality in our ECC
& SCM system. When we run SNP heuristics at the plant, system generates planned
orders at SUBC vendor location as Production (Subcontracting Planned) item
category ES - SNP: Planned Order (Subcontracting).

 

When we try to run SNP heuristic Capacity leveling with capacity
overloaded, system is not capacity leveling across the periods.

But SNP Heuristic Capacity leveling works with EE - SNP: Planned order Type.

 

Anyone had experienced the same?


Product and its description in separate columns in Planning Book

$
0
0

Hi all,

   I am using Planning book for Production Planning on Weekly/Daily basis. In that, while downloading the APO Product, we get it as - APO PRODUCT No/ Descrition in one single column.

 

For Eg. 234XXXX/ ARCTIC WHITEXXXXXX BSIV

 

I want to view the above said example in the 2 different columns. Please suggest the way out

 

 

Thanks & Regards,

Sagar

Missing Selection Icon (Flower Icon) in ELM planning book..Can anyone please help

$
0
0

Missing Selection Icon (Flower Icon) in ELM planning book..Can anyone please help

confirmation activity:start time greater than remaining start time

$
0
0

Hello Experts

 

While CIFing Production orders I am getting the above error "confirmation activity:start time greater than remaining start time". or sometimes the error says "invalid confirmed start time of an activity"

 

I have checked the inter operation times for the operations & have ensured that the Min & max values are same.

 

I have attached the screen shot also.

 

Kindly advise

 

Regards

Soumerror 1.png

APO Planned Orders to R/3

$
0
0

Hi Team,

 

We are running MRP in our APO system. APO generates planning proposals (Eg: planned orders) for next 6 months. But R/3 team would like to receive the planned orders for only next 3 months. Is this possible to restrict only to send the next 3 months planned orders in stead of next 6 months planned orders to R/3 from APO?

 

Thanks

SPP : How to read Demand : Final History key figure

$
0
0

Hello Experts,

 

I have a reporting requirement where I want to display "Demand : Final History" key figure data, as available under the /SAPAPO/SPPDMDH planning book.

 

Could you please suggest how to extract this key figure data???

 

Appreciate your help.

 

Regards,

Mahendra

Viewing all 2068 articles
Browse latest View live


<script src="https://jsc.adskeeper.com/r/s/rssing.com.1596347.js" async> </script>