I am new to the Deployment/Optimizer area. I have modeled a scenario as described below.
And have a few questions on what I would like to happen during deployment.
Central DC: CDC1, Regional DCs: RDC1 & RDC2
Product gets deployed from Central CDC1 to RDC1 & RDC2. I have customer demand and forecasts at all the three locations.
I have defined ATD Receipts category group as just Stock on hand only (category CC) and ATD Issues includes AY, BH, BI,
BM, BR, EB etc. These two categories are assigned to the Location Master.
I have specified Fair Share Rule "A" in the Product master and location dependent penalty costs in SNP1 tab.
In the Deployment Optimizer profile I have mentioned that the Distribution is based on Lowest Costs for both Supply Shortage
and Supply Surplus. I have defined a Pull Depl. Horizon of 10 days, and blank for Push Deployment and SNP Checking Horizon.
When I run the deployment with all the three locations, what I notice is that the Customer orders and forecast of the Central DC are
satisfied before deploying anything to the Regional DCs.
My requirement is that the Central DC should deploy the available quantity at the Central equally among the Centrals and the Regional
DCs on a fair share basis for the Sales orders first, then the remainder of the stock should be deployed, again among Central and
Regional DCs on a fair share basis for the forecast and the safety stock is the last.
How can I achieve this equal deployment among central and regionals even though Central is the source location.
Could somebody let me know how to model this above requirement?
Thanks,